A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
Home
Agile
A team finishes developing all of their Stories in the first six days of the Iteration, tests them...
+3
votes
asked
Jun 17, 2019
in
Agile
by
tempuser123
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
#safe-agile
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Jun 17, 2019
by
tempuser123
They are waterfalling the Iteration
Your comment on this answer:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Related questions
+4
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
#agile-process
#agile-vs-scrum
#agile-methodologies
#what-is-safe
#safe-agile
#safe-methodology
+1
vote
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Dec 26, 2019
in
Agile
by
srikanth
0
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Dec 15, 2019
in
Agile
by
anonymous
0
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving
asked
Dec 12, 2019
in
Agile
by
sudana
0
votes
Q: a team finishes developing all their stories in the first six days of iteration
asked
Mar 13, 2020
in
Agile
by
yourell
+5
votes
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?
asked
Jun 17, 2019
in
Agile
by
tempuser123
#safe-agile
#agile-safe
#agile-lean
+1
vote
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
asked
Dec 26, 2019
in
Agile
by
srikanth
0
votes
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
asked
Dec 12, 2019
in
Agile
by
sudana
iteration
agile
+1
vote
Q: Continuous Deployment (CD) has six elements that, when followed, keep each team member, team, and the Agile Release Train on track. Which two statements best describe elements of CD?
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
#agile-process
#agile-vs-scrum
#agile-methodologies
#what-is-safe
#safe-agile
#safe-methodology
+5
votes
Q: Continuous Deployment (CD) has six elements that, when followed, keep each team member, team, and the Agile Release Train on track. Which two statements best describe elements of CD?
asked
Jun 17, 2019
in
Agile
by
tempuser123
#safe-agile
...