You have been asked to estimate the story points for a particular story using the Fibonacci

sequence. You have reviewed the story, but it seems to indicate a significant amount of work and

a number of unknowns, particularly around the creation of test data. At this point, you don’t know

if you’ll be able to use existing data or will have to create your own. You also don’t know how you

will test the interfaces between this story and the existing code.

Given this information, what would be the proper value to assign in story points?

a. 1

b. 5

c. 13

d. 18