0 votes
in Agile by
Describe what happens in the sprint planning meeting?

1 Answer

0 votes
by

The work to be performed in the Sprint is planned at the Sprint Planning. This plan is created by the collaborative work of the entire Scrum Team. Sprint Planning answers the following:

What can be delivered in the Increment resulting from the upcoming Sprint?

How will the work need to deliver the Increment be achieved?

By the end of the Sprint Planning, the Development Team should be able to explain to the Product Owner and Scrum Master how it intends to work as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment.