0 votes
in Agile by

A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving

Related questions

0 votes
asked Mar 13, 2020 in Agile by yourell
+1 vote
asked Jul 31, 2019 in Agile by sheetalkhandelwal
...