On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
Home
Agile
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13...
asked
Dec 12, 2019
in
Agile
by
sudana
retagged
Nov 17, 2022
by
sharadyadav1986
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action
iteration
agile
0
Answers
Related questions
+1
vote
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
asked
Dec 26, 2019
in
Agile
by
srikanth
+5
votes
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?
asked
Jun 17, 2019
in
Agile
by
tempuser123
#safe-agile
#agile-safe
#agile-lean
0
votes
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories.
asked
Nov 7, 2019
in
Agile
by
sachatouille
+1
vote
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories.
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
0
votes
Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?
asked
Dec 26, 2019
in
Agile
by
srikanth
0
votes
Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?
asked
Nov 6, 2019
in
Agile
by
sachatouille
+5
votes
James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?
asked
Jul 29, 2019
in
Agile
by
sheetalkhandelwal
#agile-development-methodology
#agile-training
#agile-software
#agile-process
#agile-vs-scrum
#agile-methodologies
#scaled-agile-framework
#safe-agile
#agile
definition
0
votes
What are the advantages of maintaining consistent iteration (timebox) lengths throughout the project?
asked
Apr 23, 2021
in
Agile
by
rajeshsharma
iteration
agile
testing
+1
vote
The product owner is leading the Team to decide which features they should include in the Sprint Backlog first.
asked
Apr 22, 2021
in
Agile
by
SakshiSharma
agile
agile-testing
0
votes
If a team can complete 10 story points In an iteration then how long will it take for the team to complete 100 story points?
asked
Apr 20, 2021
in
Agile
by
rajeshsharma
agile
planning
agile-mcq
agile-mcq-2021
agile-interview-questions
agile-questions-answers
+1
vote
An earthquake damaged your construction project. Your contractor says that he cannot fulfill the terms of the contract due to a specific clause you both had signed the contract. He is referring to the:
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
+1
vote
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Dec 26, 2019
in
Agile
by
srikanth
0
votes
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Dec 15, 2019
in
Agile
by
anonymous
0
votes
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving
asked
Dec 12, 2019
in
Agile
by
sudana
+4
votes
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
#agile-process
#agile-vs-scrum
#agile-methodologies
#what-is-safe
#safe-agile
#safe-methodology
+3
votes
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Jun 17, 2019
in
Agile
by
tempuser123
#safe-agile
0
votes
Assume you want to cluster 7 observations into 3 clusters using the K-Means clustering algorithm. After first iteration, clusters C1, C2, C3 have following observations:
asked
Mar 20
in
Clustering - The Data Ensemble
by
john ganales
iteration
clusters
k-means
clustering
0
votes
While performing a cost-benefit analysis, the Product Owner of a project determined that the project has 45% probability of incurring a loss of $800,000
asked
Dec 16, 2022
in
Agile
by
rajeshsharma
agile
0
votes
on the seventh day of the iteration
asked
Dec 12, 2019
by
sudana
0
votes
How do you deal with a Product owner who assigns user stories/tasks to the individual team members?
asked
Jan 19, 2020
in
Agile
by
rajeshsharma
#po-tasks
...