On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
Home
Agile
On the seventh day of the Iteration, the team realizes that they will...
asked
Dec 12, 2019
in
Agile
by
sudana
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action
Please
log in
or
register
to answer this question.
0
Answers
Related questions
+1
vote
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
asked
Dec 26, 2019
in
Agile
by
srikanth
+4
votes
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?
asked
Jun 17, 2019
in
Agile
by
tempuser123
#safe-agile
#agile-safe
#agile-lean
0
votes
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories.
asked
Nov 7, 2019
in
Agile
by
sachatouille
+1
vote
Q: On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories.
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
0
votes
Q: Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?
asked
Dec 26, 2019
in
Agile
by
srikanth
0
votes
Q: Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?
asked
Nov 6, 2019
in
Agile
by
sachatouille
+4
votes
Q: James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?
asked
Jul 29, 2019
in
Agile
by
sheetalkhandelwal
#agile-development-methodology
#agile-training
#agile-software
#agile-process
#agile-vs-scrum
#agile-methodologies
#scaled-agile-framework
#safe-agile
#agile
definition
+1
vote
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Dec 26, 2019
in
Agile
by
srikanth
0
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Dec 15, 2019
in
Agile
by
dsione003
0
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving
asked
Dec 12, 2019
in
Agile
by
sudana
+4
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
#agile-process
#agile-vs-scrum
#agile-methodologies
#what-is-safe
#safe-agile
#safe-methodology
+2
votes
Q: A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
asked
Jun 17, 2019
in
Agile
by
tempuser123
#safe-agile
0
votes
Q: on the seventh day of the iteration
asked
Dec 12, 2019
by
sudana
0
votes
Q: How do you deal with a Product owner who assigns user stories/tasks to the individual team members?
asked
Jan 19, 2020
in
Agile
by
rajeshsharma
#po-tasks
0
votes
Q: The product owner is leading the Team to decide which features they should include in the Sprint Backlog first.
asked
Apr 22, 2021
in
Agile
by
SakshiSharma
agile
agile-testing
...